Decision · Hero decision
FSF-02 reline liner plates at risk — approve replacement supply
At riskAwaiting approval
- Asset
- Flash Smelting Furnace #2
- Exposure
- $1,100,000
- Raised
- 2 days ago
What the agent found
Agent brief
PO-4471 to RefracTech for 4 × RLP-3400 is unacknowledged after 9 days and now arrives after the FSF-02 reline start. The reline protects a $1.1M/day line. Agent sourced qualified alternates and recommends re-sourcing to Thermalloy.
3 ranked
Sourced options
- ARe-source to Thermalloy s.r.o.Thermalloy s.r.o.· Recommended28 Julin 13 days8 days early$67,200+$8,200
- BOrder from Kermas Refractories LtdKermas Refractories Ltd5 Augin 21 dayson the deadline$56,400−$2,600
- CHold for RefracTech GmbHRefracTech GmbH16 Augin 32 days11 days late$59,000$0