Pirin Copper AD
Zlatitsa, Bulgaria
Decision queue
Agent orchestration

How the agent reached this recommendation

Tervel's agent read the live procurement data, worked the problem end to end, and prepared one call for you.

1 · The data it read
PO-4471 · unacknowledged 9 days
RefracTech GmbH — the current order
4× RLP-3400
Refractory liner plates · $59,000
FSF-02 reline starts in 21 days
The hard deadline
Current order lands 6 days late
Line down · $1.1M/day
2 · What the agent did
  1. 1Flagged PO-4471 at risk
  2. 2Emailed RefracTech chasing acknowledgment
  3. 3Parsed RefracTech reply
  4. 4Sourced qualified alternates
3 · Its recommendation
Recommended

Re-source to Thermalloy s.r.o.

Thermalloy s.r.o. · 96% on-time

Arrives
8 days early
New order
PO-4472 · $67,200
vs original
+$8,200

Cancels PO-4471. Both execute on your approval below.

Act 1

Why it can't wait

FSF-02 · FSF-02 Refractory Reline — Campaign 7

Reline schedule vs. this orderParts arrive 6 days late
Today
Reline must start
5 Aug · in 21 days
Parts arrive
11 Aug · in 27 days

The parts land 6 days after the line must already be down — and every day of that gap costs $1.1M/day.

Act 2

The agent's full trail

Every step, with the emails it sent and parsed

  1. Cross-checked PO-4471 against the FSF-02 reline calendar. RefracTech quoted an 18-day lead from acknowledgment, but the PO has been unacknowledged for 9 days. Earliest realistic arrival lands 6 days after the reline deadline — a gap on the primary smelting line ($1.1M/day).

  2. Sent a priority follow-up to orders@refractech.de requesting acknowledgment and a firm dispatch date for the 4 × RLP-3400 liner plates on PO-4471.

  3. RefracTech replied citing a production backlog and roughly a two-week delay. Parsed new delivery is ~32 days out — 11 days past the reline deadline. The original order can no longer protect the window.

  4. Queried the qualified vendor list for RLP-3400-equivalent liner plates. Two viable alternates: Thermalloy s.r.o. (12-day lead, 96% reliability) and Kermas Refractories Ltd (20-day lead). Ranked options and prepared a replacement PO to Thermalloy for approval.

  5. Recommendation ready: re-source to Thermalloy (Option A). PO-4472 is drafted and the PO-4471 cancellation is prepared. Both execute on approval — delivery in 13 days, 8 days before the reline.

Act 3

The decision

Three sourced options, ranked

A
Re-source to Thermalloy s.r.o.
Thermalloy s.r.o.·96% on-time
Recommended
Arrival
28 Jul
in 13 days
vs reline deadline
8 days early
Total
$67,200
+$8,200vs original POvs $1.1M/day at risk

Preferred vendor, 96% on-time reliability. Delivery in 13 days gives an 8-day buffer before the reline deadline. +$8,200 over the original PO is trivial against $1.1M/day of primary-line downtime risk.

B
Order from Kermas Refractories Ltd
Kermas Refractories Ltd·88% on-time
No safety margin
Arrival
5 Aug
in 21 days
vs reline deadline
on the deadline
Total
$56,400
−$2,600 vs original PO
C
Hold for RefracTech GmbH
RefracTech GmbH·71% on-time
11 days late
Arrival
16 Aug
in 32 days
vs reline deadline
11 days late
Total
$59,000
Same cost as original PO
Recommended
Re-source to Thermalloy s.r.o.

Demo state is in-memory — reloading the page also resets it.